What We Built
The short version. One boarded lift, erected and struck inside a single visit, standing entirely on a private driveway about three miles from our yard. No highway licence, no application to the council, no fee, and the household kept its parking throughout.
A semi detached house in Sevenoaks, tile hung above and rendered below, with an integral garage and a block paved drive running up to it. The guttering needed work.
What went up was a single boarded lift running the width of the front elevation, with the standards carried up past it to the roofline and a ladder tied on for access. Guardrails to the open edge. Nothing more complicated than that, because nothing more was needed.
Every standard lands on the block paving rather than on soft ground, spread properly so the load goes into the drive and not into one paviour. Block paving looks solid and is bedded on sand, so a standard dropped straight onto it without a sole board is how you end up replacing somebody's driveway at the end of a gutter job.
Why Gutter Work Needs More Than a Ladder
Clearing leaves out of a gutter is a ladder job. Repairing one is not, and the difference is in what your hands are doing.
On a ladder you have one hand on the rungs and one hand free, one point of contact, and nowhere to put anything down. Refixing brackets, replacing a length of guttering or sorting a joint that has dropped all need two hands, a few tools within reach and something to rest a section on while you line it up.
There is a time argument as well. Guttering runs the width of a house. Off a ladder you fix a bit, climb down, move the ladder, climb up, fix the next bit. Off a boarded platform you walk along it. The scaffold costs money and saves more of it than people expect on anything longer than an afternoon.
| Structure | One boarded lift, full width of the front elevation |
|---|---|
| Access | Ladder, tied |
| Edge protection | Guardrails and toe boards to the open edge |
| Standards | Landed on sole boards over block paving |
| Built to | TG20:21, by CISRS certified scaffolders |
| Inspection | Before first use, then at intervals of no more than 7 days |
| Highway licence | None required. Entirely within private ground |
| Distance from our yard | About 3 miles |