What We Built
The short version. Twenty houses, all built to the same design, all needing the same roofing work. That changes the job. A one off scaffold is a problem you solve on the day you arrive. Twenty identical houses is a problem you solve once and then repeat nineteen times.
A boarded working lift at eaves level, running the width of the worked half and returning around the side elevation. It sits just under the gutter, which is the height the roofers want for the eaves course and the gutter line.
Above the boards, a double guardrail with mesh brickguard panels and debris netting behind them. Below, standards running to the ground.
Where the standards cross the path to the front door, they are padded. That is the detail most people never notice and the one the residents feel every day.
Why Twenty Identical Houses Is a Different Job
On a single house the scaffold is designed around what you find when you turn up. On a repeat programme the scaffold is designed once, properly, and then it is a kit.
That is worth more than it sounds. The gear is counted once rather than guessed at twenty times. The erection sequence settles after the first two or three and then the crew are quicker on every house after that. The tie pattern is proven on the first one rather than re-worked on each.
It also means the client gets the same scaffold at number four as at number twenty, which on a contract where somebody is signing off handovers matters more than it does on a one off job.
The risk runs the same way. A detail that is slightly wrong does not stay a small problem. It becomes twenty small problems, and on the twentieth house somebody is still working around it.